COMPARTMENTING AND FIRE PROOFING SEALINGS

PM 018 - MASONRY WALL

CROSSING OF THE DUCT WITH FIRE PROOFING AIRLOCK OUT OF ALIGNMENT BIG HOLE

SPECIFICATION

 

  • KM-FC180 COVER made up of two glass fibers fabric sheets, one of them is covered with aluminium, inside there is a ceramic paper sheet covered with aluminium between to layers of ecological bio soluble felt for high temperature

  • KM-FF108 graphitic intumescent material

  • KM BOARD V1 mineral fiber panel, 150kg/m³ density with fire resistant coating on one side

  • KM SEALER F is a single component intumescent putty

  • KM-ALU aluminium adhesive tape

 

FITTING UP

 

Lag the duct with KM-FC180 COVER and overlap the edges of 10 mm at least. Fix cover with steel wire and adhesive aluminium tape KM -ALU

Shape KM-FF108 and KM BOARD V1 panel and set up them back to back with the coated sides outwards; the perimeter of both sides against wall and duct must be sealed with fire resistant putty KM SELAR F

 

CERTIFICATION

 

  • LAPI 14, pos.14.

 