COMPARTMENTING AND FIRE PROOFING SEALINGS
PM 018 - MASONRY WALL
CROSSING OF THE DUCT WITH FIRE PROOFING AIRLOCK OUT OF ALIGNMENT BIG HOLE
SPECIFICATION
-
KM-FC180 COVER made up of two glass fibers fabric sheets, one of them is covered with aluminium, inside there is a ceramic paper sheet covered with aluminium between to layers of ecological bio soluble felt for high temperature
-
KM-FF108 graphitic intumescent material
-
KM BOARD V1 mineral fiber panel, 150kg/m³ density with fire resistant coating on one side
-
KM SEALER F is a single component intumescent putty
-
KM-ALU aluminium adhesive tape
FITTING UP
Lag the duct with KM-FC180 COVER and overlap the edges of 10 mm at least. Fix cover with steel wire and adhesive aluminium tape KM -ALU
Shape KM-FF108 and KM BOARD V1 panel and set up them back to back with the coated sides outwards; the perimeter of both sides against wall and duct must be sealed with fire resistant putty KM SELAR F
CERTIFICATION
-
LAPI 14, pos.14.